Answer:
Option C
Explanation:
1 child 1 day work $=\frac{1}{192}$
1 adult 1 day work $=\frac{1}{96}$
Work done by 16 adults in 3 days $=\frac{1}{96}\times 16\times 3$ $=\frac{1}{2}$
Remaining work $=\left(1-\frac{1}{2}\right)$ $=\frac{1}{2}$.
(6 adult + 4 children ) 1 day work $=\left(\frac{6}{96}+\frac{4}{192}\right)$ $=\frac{1}{12}$
$\frac{1}{12}$ work is done by them in 1 day
$\frac{1}{2}$ work is done by them $\left(12\times \frac{1}{2}\right)$ = 6 days